Killingworth Paper Subdivision

News Feed

  • August 2024 update

    Construction of the Stage One works commenced in July 2024 with the following works having been completed to date:

    • Site establishment and preparation works
    • Installation of nest boxes to offset the removal of cleared hollows
    • Commencement of sewer infrastructure installation within The Boulevarde laneway

    The works are being undertaken by local civil contractor Centurion Civil who were engaged after a successful tender process. The current estimated date for completion has been extended from late August to mid-October due to ongoing unfavourable weather conditions and the significant amount of rock being excavated.

    Thank you to all participating landowners for your diligence in meeting the landowner agreement contribution requirements. All payments are currently up to date.

    If you have any enquiries regarding invoicing or the project, please do not hesitate to contact Land Development Officer Andrejs Rubenis at [email protected] or phone 4921 0026.