  • December 2024 update

    Construction of the Stage One servicing works is now nearing completion and is on track to be completed before Christmas.

    The next steps for the project following construction include:

    • prepare and register positive covenants on lots outlining future development requirements (a condition on the Hunter Water approval)
    • finalise the certification process with Hunter Water (Section 50 certificate)
    • issue the final invoice for the landowner agreement payments.

    Once the Section 50 certificate is obtained from Hunter Water, the project will be completed and the lots will be ready for development.

    The adverse weather and significant amount of rock encountered has caused significant delays throughout the construction phase of this project. We have appreciated your understanding and patience.