Killingworth Paper Subdivision

News Feed

  • June 2024 update

    05 Jun 2024

    Since the last project update, we have been making exciting progress towards the delivery of the Stage One servicing works including:

    • finalising all design works and approvals with Hunter Water
    • seeking quotations via a tender process for the construction works
    • successfully engaging a contractor to undertake the construction works.

    Based on the current works program submitted by the engaged contractor, works will commence mid-June and be completed by late August 2024, weather permitting.

    As the works are about to commence, please be mindful of the due dates for the invoices issued for the landowner agreement contributions. A statement summary will be issued to each landowner this month.

    Summary of upcoming project steps include:

    • construction to commence mid-June
    • construction due for completion late-August
    • resolution of final landowner agreement contribution invoices.

    If you have any enquiries regarding invoicing or the project, please do not hesitate to contact Land Development Officer Andrejs Rubenis at [email protected] or phone 4921 0026.